Registration of Constructors and Employers Engaged in Construction
Before beginning work at a construction project. The form is not submitted to the Ministry, but must be kept at the project while the employer is working there.
02Employer's Report of Injury/Disease
WSIB must receive the complete employer accident report within three business days after the employer learns of the reporting obligation.
03Notice of Project
Before construction begins on projects meeting section 6 triggers, including projects expected to exceed $50,000 in labour and materials, or $250,000 for projects confined to automobile manufacturing or assembly factories.
04Joint Health and Safety Committee Requirement
Establish and maintain a JHSC when the workplace threshold applies. Most workplaces with 20 to 49 workers require at least two JHSC members; 50 or more require at least four.
05Proper Invoice Deficiency Notice
Written deficiency notice must be delivered within 7 days of receipt when disputing invoice form or structure.
0628-Day Prompt Payment Timeline
Track the 28-day owner payment timeline from receipt of a proper invoice unless the Act permits a valid notice response.
07Form 6 Annual Holdback Release
For contracts extending beyond one year, publish Form 6 within 14 days after each contract anniversary.
0860-74 Day Holdback Payout Window
After Form 6 publication, payment of accrued basic holdback must be tracked for day 60 through day 74 when no liens are preserved.
09ODACC 90-Day Adjudication Deadline
Track the 90-day post-completion, abandonment, or termination adjudication window for eligible disputes.
10Construction Act Section 27.1 Repeal
Do not rely on the former section 27.1 notice-of-non-payment mechanism to refuse holdback for deficient or incomplete work.
11Substantial Performance Payment Closeout
Track substantial performance publication, deficiency closeout, invoice intake, and holdback release events in one administrative window.
12Notice of Non-Payment Prompt Payment Control
Track notice of non-payment steps and downstream communication windows when a payer disputes payment after receiving an invoice.
13Change-Order Documentation Compliance
Document changed work before billing, including directive date, backup, approval authority, and invoice connection.
14Construction Lien Risk Tracking
Track lien-risk status before annual holdback release, final holdback release, and closeout payment events.